Day 34 to 49

“Day 34 To Day 49” Shamrock Log Home Construction

Click Here For Free Quote

Day 34

October 11th, Monday

Day 34 – Electricians onsite met with the Owner’s and laid out all electric and installed all ceiling drops with wiring rough. Exterior metal clad windows and doors delivered. Crew installing insulation, roof decking

Shamrock Construction Day 34
Day 34
Shamrock Construction Day 34
Day 34
Shamrock Construction 3 Day 34
Day 34
Shamrock Construction Day 34
Day 34

Day 35

October 12th, Tuesday

Day 35 – Crew installing insulation, roof decking and working on porches. Building Dept. on site today and signed off on sheathing inspection.

Shamrock Construction Day 35
Day 35
Shamrock Construction 2 Day 35
Day 35

Day 36

October 13th, Wednesday

Day 36 – Crew working on porches.

Shamrock Construction Day 36
Day 36
Shamrock Construction 2 Day 36
Day 36

Day 37

October 14th, Thursday

Day 37 – Crew working on porches and installing roof underlayment

Shamrock Construction Day 37
Day 37

Day 38

October 15th, Friday

Day 38 – Crew working on interior wall framing. Plumbers onsite working on rough in.

Shamrock Construction Day 38
Day 38

Day 39-40

October 16th, Saturday

Day 39 – Crew working on interior wall framing. Plumbers onsite working on rough in.

Day 40 – October 17th, 2010 Sunday – No Work

Shamrock Construction Day 39
Day 39

Day 41

October 18th, Monday
Day 41 – Crew working on window and door bucking and front covered porch system. Plumber onsite working on rough in.

Shamrock Construction Day 41
Day 41

Day 42

October 19th, Tuesday

Day 42 – Crew working on window bucking and bay window. Plumbers onsite working on rough-in. Electricians onsite working on rough-in. Hardwood and tile subcontractor onsite measuring layout for finish floors and shower hops.

Shamrock Construction Day 42
Day 42

Day 43

October 20st, Wednesday

Day 43 – Crew installing windows. Framing bay window. Plumbers onsite working on rough-in and installing waterline to well.

Shamrock Construction Day 43
Day 43
Shamrock Construction 2 Day 43
Day 43
Shamrock Construction 3 Day 43
Day 43

Day 44-46

October 21th, Thursday
Day 44 – Crew framing 6/0 x 6/10 doors. Completing log to roof transition. Framing bay window.

October 22nd, Friday
Day 45 – Crew working on misc. items, HVAC crew onsite, met with the owner and laid out all vents/returns and installed ductwork.

October 23rd, Saturday
Day 46 – Crew working on misc. items

Shamrock Construction Day 45
Day 45
Shamrock Construction 2 Day 45
Day 45
Shamrock Construction 3 Day 45
Day 46

Day 47-48

October 24th, Sunday

Day 47 – No Work

October 25th, Monday
Day 48 – Crew working on misc. items, drop ceilings, elect. cutouts, finished sheathing bay window and set both 6/0 x 6/10 exterior doors. H.V.A.C crew onsite, met with owner and laid out last 2 vents that were in conflict with floor structural members. “H.V.A.C rough-in complete.” Plumbers onsite, set tub and finishing rough-in. Metal roof contractor onsite taking finish roof measurements and ordered metal to be delivered tomorrow. Coordinated and completed all roof penetrations with roofing contractor (H.V.A.C, Plumbing, and Gas) Metal roof installation scheduled to start Wednesday.

Shamrock Construction Day 48
Day 45

Day 49

October 26th, Tuesday

Day 49 – Crew working on misc. items and framing fireplace. ” Plumbers onsite, finishing rough-in. Metal roofing delivered. Meeting onsite with owners to discuss porch rails and picket design.